Luoyang Hongyuan Bearing Technology Co., Ltd.
Installation, two-stage filtration and furnace cleaning completed in four days; both customer re-checks passed.
Background
The quench furnace and salt bath had run for years. A thick deposit had built up inside the furnace, and the molten salt carried visible suspended solids. Both temperature uniformity and salt cleanliness had degraded, and the customer wanted them addressed without a long shutdown.
What we did

Furnace interior cleaning
Equipment arrived on 4 March and was installed by 16:52; piping and cabling were completed on 5 March with three operators on shift.
On 6 March the bath was filtered and re-filtered with a fresh screen to improve fine-particle capture.
From 7 to 8 March the furnace interior was cleaned while filtration of the salt bath continued.
What changed
- The customer sampled on 7 and 8 March; both checks passed.
- With the furnace cleaned, temperature uniformity recovered and suspended solids in the bath dropped noticeably.
- Equipment was demobilised after joint confirmation, closing the job in four days.



Other cases

Luoling Bearing
Eighteen days of continuous on-line filtration turned a black, turbid salt bath into a clear one.

Hailin Zhongke
A cross-province campaign: transfer filtration plus furnace cleaning, both passed re-inspection — followed by a quench-oil filtration contract.
Tell us what your bath is doing.
We will tell you what to do next.
One call is enough to establish three things: where your bath stands today, which step comes first, and how long it takes.